Started by Bruce Momjianabout 22 years ago3 messages
#1Bruce Momjian
pgman@candle.pha.pa.us

What is the current schedule for RC2/final?

-- 
  Bruce Momjian                        |  http://candle.pha.pa.us
  pgman@candle.pha.pa.us               |  (610) 359-1001
  +  If your life is a hard drive,     |  13 Roberts Road
  +  Christ can be your backup.        |  Newtown Square, Pennsylvania 19073
#2Tom Lane
tgl@sss.pgh.pa.us
In reply to: Bruce Momjian (#1)
Re: release timing

Bruce Momjian <pgman@candle.pha.pa.us> writes:

What is the current schedule for RC2/final?

I believe the plan is to wrap RC2 this Sunday evening, and to release
final the following Monday (11/17), barring problems. Core will make
a go/no-go release decision Thursday evening, and if it's "go" we'll
put a hard code freeze in place then, with only docs changes allowed
before the release is wrapped next Sunday.

[ core guys: that is what we agreed to, right? ]

regards, tom lane

#3Marc G. Fournier
scrappy@postgresql.org
In reply to: Tom Lane (#2)
Re: release timing

On Fri, 7 Nov 2003, Tom Lane wrote:

Bruce Momjian <pgman@candle.pha.pa.us> writes:

What is the current schedule for RC2/final?

I believe the plan is to wrap RC2 this Sunday evening, and to release
final the following Monday (11/17), barring problems. Core will make
a go/no-go release decision Thursday evening, and if it's "go" we'll
put a hard code freeze in place then, with only docs changes allowed
before the release is wrapped next Sunday.

[ core guys: that is what we agreed to, right? ]

That was my understanding as well ... gives the Advocacy crew an extra bit
of time to deal with their issues, and gives an extra week for any docs
changes to trickle in ...